The progress at Meadow View Elementary School is really exciting. Painting is underway inside the Gym and already completed in the kitchen area. 50% of the exterior windows have been installed in the grade 1-4 wing and interior framing is 90% complete. Drywall on the first floor is also nearly complete. In the 4K/5K wing, painting is 95% complete, ceiling grid installation is complete and bathroom tile and fixture installation is nearly complete. In the next month, gym equipment will be installed, along with gym lighting. The main office and library areas will also be painted within the month. Painting will also begin on the first and second floors of the grade 1-4 wing and casework installation will being in the 4K/5K wing.
Gym/Cafe Area Progress:
Above: Wall and ceiling painting is underway in the gym.
Above: Mechanical/electrical/plumbing rough-in continues in the gym.
Grade 1-4 Wing:
Above: Drywall is nearing completion in the 1st and 2nd grade classrooms.
Above: Interior framing is almost complete on the second floor where 3rd and 4th grade classrooms are located.
4K/5K Wing:
Above: Painting is 95% complete in the 4K/5K wing.
Above: The corridor of the 4K/5K wing.